The atrium glass installation continues, as does ceiling tile installation. The frame for the stained glass in the Western Conference Room is nearing completion. The pictures in this post were taken on August 8th.
Our glass supplier, Advance Glass and Mirror, focused on the atrium glass over the last few days.
This picture is of the Atrium facing west.
Ceiling tile installation continues throughout the building. These two pictures are from Pre-school rooms 1 and 2 (the first two you would see as you enter the pre-school hallway from North 5th.
Once the ceiling tiles are installed, the complex HVAC and fire safety systems will disappear.
The Axis net cam was off line last week because of construction in the IT conference room on the 11th floor of city hall. It was back on line August 7th and re-aligned on August 8th.
The stained glass framing for the western conference room continued.
These views from the roof include the entry way for the stairs and elevator.