Sanctuary Lights and Carpet

These views from September 6th visit show the new carpet and pendant lights.

Work on the baseboards is nearly complete.sanctuary baseboard finishingMost interior doors on the first floor have been installed.  This is the handbell closet on the south west corner of the sanctuary. sanctuary carpet frames bell closetHere is a view of the south east corner leading to the “back of house” and emergency exit.sanctuarycarpetThis view looking north shows the pendant lights, downlights and continuing work on the baseboards.  The open double doors frame the entry to the multi-function room between the sanctuary and youth roomsanctuary view looking north 130905This last picture is taken from the north east corner looking toward the two vestibule exits which frame the tech booth in the middle.  The two doors on the right in the back are the electric room that supplies the sanctuary and the mechanical room containing the radiant heat system.sanctuary view looking SW 130906

Roof Deck Pour Soon

Permits for the pouring of the roof deck were issued and final preparations have been completed.  The final test prior to installation of re-bar and placing of the concrete were leak tests completed August 29th.

Following the repair of one small leak plans call for the concrete to be poured after insulation and re-bar have been installed.roof leak testwater testing roof terrace water testing suspicious joint

Internal Painting and Finishing Continues

Here are pictures taken August 23rd showing progress on all levels of the church.

Sanctuary viewed from tech booth. sanctuary from tech booth 130823 View of different finished on Sanctuary floor sanctuary floor reflections sanctuary floor options -1 sanctuary floor options -2Second floor western conference room with framing for stained glass at south end.

western conference room south walladmin area 130823Pre-school hallway and class rooms. preschool hallway 16 aug preschool -1  16 aug preschool -3  16 augOur color palletcolor palletAdditional views of inside spaces. western conference room north wall patio view from third floor entryway multi purpose room 130823 kitchen 130823 front hallway prepared for painting atrium panorama looking E 130823

Interior Taking Shape (and color)

By August 16th, additional taping was completed, pre-schools were getting painted, and the preparations for the kitchen equipment begun.  Glasswork continued in the Atrium and the western conference room finishing was underway.

Pre-school hallway and classrooms were painted and tile was added to the bathrooms:preschool hallway 16 augpreschool -3  16 aug preschool -1  16 aug pre-school bathroom tile

The kitechen serving window was installed and work begun on the hood for air filtering.kitchen serving drop-down

kitchen hood 130816Atrium glass installation was completed.atrium SE view 130816

Sheet rocking in the janitors closet adjacent to the atrium was completed and preparations were made for tiling.janitors closet

Registers for the HVAC system on the first floor sanctuary are complete with additional HVAC system work also completed in the Western Conference room along with sheet rocking and painting preparation.HVAC Installation Western Conference room 130816

From across the street work on the base of the tower can be seen between the trees.tower view 130816

This picture was taken on the roof from the third floor rear stairwll looking South East toward City Hallroof view looking SE 130816.