CMU Walls Substantially Complete

The CMU (Concrete Masonry Unit) construction phase of the Church is nearly complete.

There are a few small tasks to be completed and clean-up will run into next week.  Today the hi-lifter was removing unused materials from the scaffolding.

Next week steel components that will form the basis of the second floor and roof will begin to appear on the site.  By mid-next week the Open Web Steel Joist (OWSJ) construction will begin.

The pictures below provide many views of the walls.